Sizing a Commercial Generator: A Step-by-Step Guide for Buyers
Choosing a commercial generator of the wrong size ranks among the costliest errors a business can make with backup power.
An undersized unit trips once the real load arrives, so the building loses power at exactly the moment it matters. An oversized unit costs far more than it needed to, and a diesel engine that spends most of its time under 30% of rated capacity can suffer from wet stacking. In both cases the damage falls on day-to-day operations, on the budget, and on your standing with everyone who relies on the power staying on.
Getting the size right is not difficult, but the questions have to be answered in a particular order. The steps below take you through them one at a time, so you can specify the generator confidently or go into a discussion with a supplier already knowing what to ask.
How Commercial Sizing Differs From Home Sizing
Sizing a generator for a home is fairly simple: decide which circuits need power, total their loads, add a safety margin, and the figure is done.
Commercial sizing uses the same reasoning, with several extra layers on top:
Starting Loads From Motors
Nearly every commercial building contains motor-driven equipment, such as pumps, elevators, HVAC compressors, air compressors and production machinery. At start-up an electric motor demands three to six times the load it draws while running. The generator must absorb that surge without tripping on a fault or letting voltage sag so far that other equipment drops offline.
Diversity and Demand Factor
In a commercial building the equipment does not all run at once, and a demand factor reflects that. A large office might have its lighting and HVAC on together while most outlets carry only part of their rated load. Using a suitable demand factor stops the generator from being oversized for no reason.
Harmonics
Commercial buildings today are full of non-linear loads that create harmonic distortion: UPS systems, LED drivers, variable frequency drives (VFDs) and more. Generators differ in how well they cope with it, and where harmonic content is high a larger unit may be needed to keep voltage quality acceptable.
Room to Grow
If a generator matches today's load exactly, there is nothing left for expansion. Many commercial buyers add 20 to 25% to the present load so that growth does not force a generator replacement a few years later.
Step 1: Decide What the Generator Will Power
Sizing is impossible until you know precisely what the generator has to supply. That seems self-evident, yet many buyers jump past it and ask for a recommendation while unable to answer simple questions about their own load.
Begin by sorting the loads into two groups.
Essential loads: the equipment and circuits that have to keep working through an outage to protect people and property or to let the business carry on. Typical examples are communications, security, servers, refrigeration, life safety systems, plus production machinery that cannot safely stop in the middle of a process.
Everything else counts as non-essential: circuits that can be shed during an outage without serious consequences, such as supplementary HVAC zones, decorative systems, outlets that are not critical and general lighting.
At a minimum the generator should be sized for the essential loads. Whether to cover the non-essential ones too comes down to budget and priorities.
Step 2: Work Out the Running Load
Once the essential load list is ready, the next task is to work out, in kilowatts (kW), the total running load.
Check the nameplate or specification sheet of each item and record:
- Power rating (W or kW); for horsepower, 1 HP = 0.746 kW
- Power factor, for motors (commercial motors are usually 0.8)
- Phase and voltage: 120V or 240V single phase, or 208/240/480V three phase
Adding all the running loads together gives the total connected load in kW. Then apply a demand factor that reflects how much equipment will realistically run at the same time; a demand factor between 0.7 and 0.9 suits most commercial facilities, depending on the load mix.
That figure is your running load estimate in kW.
Step 3: Allow for Motor Starting
Buyers overlook this step more than any other, and it causes more trouble than any other.
Every motor on the essential load list needs a starting kVA figure as well as its running load. At start-up a motor pulls a large surge of current, normally given as a multiple of its running current. Large motors over 50 HP may draw 6x their running current or more at start, with the starting method making the difference.
The generator has to start the biggest single motor without the unit faulting out and without voltage falling by more than 15% (the usual limit in most commercial applications). When several large motors could start together, or the biggest motor makes up a large part of the total load, motor starting becomes the factor that sets the generator size.
Soft starters and VFDs cut starting current substantially, which can let a smaller generator run larger motors. Where your equipment has them, adjust the sizing calculation to suit.
Step 4: Add a Safety Margin
With the running load known and motor starting accounted for, add a margin of 20 to 25%.
The margin does three jobs:
- It leaves headroom for load growth, so the generator does not have to be replaced
- It keeps the full-load point of the generator within 75 to 80% of its capacity rating, the ideal operating range for a diesel engine
- It lowers the chance of overload if unexpected loads are added
Compared with a unit that runs at 95% or more, a generator that normally sits in the 75 to 80% load range runs cleaner and cooler and has a longer life.
Step 5: Select the Configuration
Once the kW requirement is settled, a few specification choices remain.
Fuel
Above 20 kW, most commercial standby generators run on diesel. It packs a lot of energy into a small volume, is easy to obtain and stores well in tanks on site. If the site has a dependable gas connection, or space or permits make diesel storage difficult, natural gas or LP (propane) can be used instead. Natural gas removes the need to manage a fuel reserve on site, but it makes the generator dependent on the utility gas supply, and that can fail during a major outage as well.
Standby or Prime Rating
Standby-rated generators are designed for outages: they start automatically, run until the outage ends and then go back to standby. A standby rating is what most commercial backup generators carry. Prime-rated generators are built to run for long periods or continuously as the main source of power. Specify a prime-rated unit if grid access at your facility is unreliable or you need continuous generation.
Single Phase or Three Phase
A facility wired for three phase, or one with three phase equipment, needs a three phase generator. A single phase unit suits a commercial application that is single phase. The differences are covered in detail in our article on single phase vs three phase power for commercial generators.
Enclosure
A generator installed outdoors needs a weatherproof enclosure. Where noise matters, an acoustic or super-silent enclosure lowers the sound level considerably. Our team can help you choose an enclosure that suits your installation environment.
Typical Sizing Examples
The ranges below are rough and are meant only to show how sizing plays out in practice. Each facility is different, and these figures are no substitute for calculating the load properly.
Restaurant, small (2,000 sq ft): the essential loads are normally basic lighting, POS systems, cooking equipment and refrigeration. For single phase applications the running load typically lands between 30 and 60 kW.
Office building, small (10,000 sq ft): general outlets, lighting, a server room and HVAC. The running load usually falls in a 60 to 150 kW band, with the HVAC type and server density making the difference.
Large retail store or supermarket: in food retail, refrigeration is the biggest load. Keeping refrigeration and basic operations going in a medium-sized supermarket can take 150 to 400 kW.
Hospital or medical centre: demand is heavy, driven by HVAC, clinical equipment and life safety loads. Community hospitals commonly specify somewhere between 500 kW and more than 1,000 kW of generation, and redundancy is common.
Light manufacturing plant (30,000 sq ft): the answer depends largely on the equipment, and motor-driven production machinery adds up fast. Plants of this size often need 200 to 500 kW, and motor starting is a critical factor in the sizing.
Using the Power Requirement Calculator
As a structured first step, the power requirement calculator lets you enter your main loads and returns an estimated kW requirement. An engineer's full load assessment is still needed, but the calculator gives you a working figure to bring to a supplier.
With an estimated kW range in hand, you can browse commercial generators by kW range.
FAQ: Commercial Generator Sizing
What goes wrong when a commercial generator is undersized?
A generator that is too small overloads as soon as the connected load goes above its rated capacity. Usually it then faults and shuts down, or it runs too hot, which speeds up wear and can end in failure. In standby service, an undersized unit that faults during an outage offers no protection whatsoever.
What goes wrong when a commercial generator is oversized?
When an oversized diesel generator runs at light load, typically under 30% of rated capacity, it risks wet stacking, where unburned fuel and carbon build up in the exhaust system. The results are fouled injectors, lower power output and higher maintenance costs. Sizing the unit correctly prevents the problem, and where light loading cannot be avoided, load bank testing can keep wet stacking under control.
Is an automatic transfer switch needed with a commercial generator?
Yes, for standby applications in which the generator must start by itself when the grid fails. An automatic transfer switch detects that utility power has failed and, within seconds, switches the connected load over to the generator.
Is financing possible for a commercial generator purchase?
Many buyers fund equipment through specialist lenders. The financing page lists lenders that work with industrial equipment loans; they are independent of Global Generator Supply.
Ready to Specify a Commercial Generator?
Send us your load requirements and our team can help you specify a commercial generator that suits the facility.
Ask for a quote or consultation | Phone: +1 251-314-4812 | Work out your power requirement