Standby, Prime or Continuous: Rating a Generator Engine for the Job
Before buying a generator, start with how it will be used. The power rating an application needs can look obvious, but several factors deserve attention before you commit. The guidance below explains how drive engines should be matched to AC generator sets.
Standby Power Rating
Of all generator set ratings, standby is the most common. A standby unit's main job is to provide backup power during a utility outage, for a limited time. Units with a standby rating have no built-in overload capacity, and they must never be run together with a public utility supply, whatever the circumstances.
The standby rating applies where utility power is available. A standby engine is typically sized for an average load factor of no more than 80% and about 200 hours of running a year, of which less than 25 hours a year are spent at the full standby rating. The standby rating should be used only in genuine emergency outages. Under UL guidelines, outages arranged in advance with the utility company do not count as emergencies. Most automatic transfer switches allow manual load transfers for testing.
Prime Power Rating
Use a prime-rated generator where the user is not buying electricity from the utility. Applications of this kind divide into two categories.
Unlimited Running Time
Here the prime rating is the most power available to a variable load, with no cap on annual running hours. Over any 250-hour operating period, the average variable load should not go above 70% of the prime rating. When the engine runs at 100% of prime power, it should not log more than 500 hours a year. Avoid overloads, although the set can take a 10% overload for 1 hour in every 12 hours of running.
Limited Running Time
Limited prime power is available for a restricted number of hours with a non-variable load. It is meant for situations where an outage is expected, for example a planned reduction in utility power. Engines in these generator sets can run up to 750 hours a year at power levels below the maximum prime rating, and the prime rating must never be exceeded. Users should keep in mind that running any engine at constantly high load shortens its life. Where an application needs more than 750 hours a year, a continuous-rated engine is recommended.
Continuous Power Rating
A continuous rating is for applications that supply power continuously at 100% load with no limit on yearly hours. These units are used most often where the power grid cannot be reached, for example in mining, agriculture and military operations.
How Elevation and Temperature Affect the Rating
Take altitude and temperature into account before settling on an engine rating. For a standby rating, the engine can run at an elevation of 3,000 ft. and 100° F with no derating. For a prime rating, it can run at 5,000 ft. and 100° F with no derating. When running continuous duty high up, set the engine up to cut its output by 3% for every 1,000 ft. of elevation and by 1% for every 10° F of inlet air temperature.
ISO 3046 contains further guidance on power ratings. To pick the generator and rating that fit your needs, it is always wise to talk to a generator specialist or an electrical contractor.